Our growth progress in Muara Laboh Unit-2 Project

Apr, 16 2026
By:
In: News Release
header

As of March 2026, Supreme Energy Muara Laboh continues to make strong strides in the development of Unit 2.

 

Since the commencement of the Stage 2 EPC Contract in April 2025, key milestones have been successfully achieved, including the completion of civil works for two well pad expansions, as well as the construction of a new access road and well pad.

 

Construction is now advancing within the power plant area, with foundation works for the turbine generator and powerhouse currently underway.

 

This progress reflects the dedication and collaboration of the entire team as we move closer to delivering sustainable energy for Indonesia. Let’s keep the momentum going.