Building Momentum at Supreme Energy Muara Laboh Unit 2!

 

As of October 2026, the EPC Stage 2 Development of PLTP Muara Laboh Unit 2 has reached 73% overall progress 

 

Major equipment has arrived on-site, with most already installed. Another significant milestone is the completion of the turbine generator table-top structure, marking an important step forward in the development. 

 

Meanwhile, drilling activities have successfully completed 3 production wells and 2 injection wells, bringing us closer to the next phase of development. 

 

Every milestone brings us one step closer to delivering more clean and reliable geothermal energy for Indonesia.